Project Overview
PROJECT CONTRACT DETAILS |
SCOPE OF WORKS |
||
Location |
Huraymila, Saudi Arabia |
Complete Civil & Electro-Mechanical Work for Wind Turbine to generate 2.75 MW |
|
Owner |
Saudi Electricity Co. |
||
Consultant |
BAUWERK |
||
Main Contractor |
GE Renewable Energy |
||
Contract Amount |
2,000,000 USD |
Total Site Development Area |
90000 m2 |
Year of Completed |
2017 |
Total Volume of Reinforced Concrete |
450 m3 |
|
|
Total Weight of Rebar's |
54000 Tons |